An end item​ "A" is assembled from two​ "B" components and two​ "C" subassemblies. The​ "C" subassembly is composed of one of each component​ "B" and​ "D." If the gross requirement for​ "A" is 100​ units, what is the demand for component​ "B"?

Respuesta :

wueseterijever wueseterijever
  • 18-03-2020

Answer:

400 units

Explanation:

Answer Link

Otras preguntas

I need help with my homework please answer this correctly
a company borrowed 25000 at 3.5% and was charged 2625 and interest how long will it take for the company pay
How were the North American different from the civilizations that developed in Mexico, Central America, and South America?
How do I solve K=PRT for T
A _____ is a digital media file distributed over the Internet using syndication feeds for playback on mobile devices and personal computers.
8,9,10 show work plz
What was the Black Panther Party
Six times a number plus 4 is the same as the number minus 11.
Amount (mol) of Mn atoms in 62.0 mg of Mn
The issuance of a warrant ensures a more orderly procedure and is a better guarantee that probable cause is, in fact,present because it has been reviewed by a(n