If it takes 3 days for 10 workers to finish building one house, how many days will it take 15 workers to finish 4 houses?

Respuesta :

sirinda
sirinda sirinda
  • 19-10-2017
a = house
3 days x 10 worker = a
a = 30 work unit
4a = 120 work unit
120 work unit = 15 workers * y days
y = 120/15 = 8 days

i hope this isn't too confusing 
Answer Link

Otras preguntas

What is the difference between historical time and a quantity of time
Find the value of L. Perimeter = 22. Width is 3. So what is L? On a rectangular
How do plant populations in a community change over time?
if de has endpoints D(-1,6)and E(3,-2),then the midpoint M of DE lies in Quadrant1
Round 51,487 to the nearest thousands
A bedroom is 5.2 meters wide. find its width in feet
What continent is also a country? what is the capital?
Place the decimal point in the answer to make it correct. Explain your reasoning. 3.9853X8.032856 = 32013341.
who killed abe Lincoln?
4x(12+14)= ? +(4x14)