contestada

a company planned to finish a project with 80 people in 80 days.if after the initial 10 days,the number of people reduces to 70,by how many days will the project get delayed?​

Respuesta :

Аноним Аноним
  • 17-10-2021

Answer:

10 days delay

Step-by-step explanation:

in ten day 12.5% work done by 80 peoples

then 87.5% work hsas to be done by 70 peoples

the days consoder as 'x'

then( 70/x)*100 = 87.5

1/x = 87.5/7000

x =7000/87.5

x =80

so 70 peoples take 80 days to finish the work

so 10 days delay

Answer Link

Otras preguntas

Solve the equation ?
If 147 g of znf2 (ksp = 0.0300) is added to water to make a 1.00 l solution, what is the [f−] concentration in the solution in molarity?
In what ways does Japan express its' nationalism in 1920's and 30's?
Nora has 4 candles on her cake. Maria has 9 more candles than Nora . How many candles Maria have ?
What is the factored form of 6x2 + 11x – 10?
How do fires help succession?
what evidence is there that maos great leap forward was a failure
When applicants who score within a certain score range are considered to have scored equivalently ________. select one: a. top-down b. criterion-related c. mini
Which attributes does the exosphere have? high temperatures and low gravity low temperatures and low gravity low temperatures and high gravity high temperatures
1. Which recipe was your favorite recipe? 1 b. List 3 Reasons why the chosen recipe was your favorite. 2. What method of cooking was used for each recipe?