7 men can dig a canal in 14 weeks. After 2 weeks of work another 7 men joined them in how many weeks more will the work be finished?

Respuesta :

Yournotmopid Yournotmopid
  • 16-11-2020

Answer:

1 week

Step-by-step explanation:

Answer Link

Otras preguntas

Need a answer for 1. And 2. Not the top one that is cut of
Can someone please help me graph y = 2x - 7
if the length of the container is half of a foot longer than it’s width what expression represents the height of the container
What is the answer to the question above
The sum of two integers is -8 and their product is -20 What are the integers?
what is the LCM of 95 and 14
A bell with a fundamental frequency of 880 Hz is moving toward an observer at 3.5 m/s. If the speed of sound is 343 m/s, what pitch would be heard by the observ
In a recent​ year, person A and person B had two concert​ tours, and together they generated $ 192.4 million$192.4 million in ticket sales. If person B took in
Select one option which does not belong: a. bañarse b. ducharse c. lavarse d. ponerse
What value of x makes this addition sentence true?