Profit, time and performance are all basic classifications of project priorities.
a) true
b) false

Respuesta :

jepessoa
jepessoa jepessoa
  • 18-08-2020

Answer:

b) false

Explanation:

The basic classifications of project priorities are cost, time and performance. Profit is not included in the list, cost is included.

A project manager must decide how to manage the trade offs between cost, time and performance. E.g. if you want something well done and cheap, you cannot expect to have it done fast. If you want something done well and fast, it wouldn't be cheap.

Answer Link

Otras preguntas

Solve the question attached.NO SPAM!!Well explained Answers needed:)​
...they...off the lights before leaving clash
What does Kenya, Nigeria and South Africa’s government all have in common
PLEASE HELP!!! The population P of a small town, measured in hundreds, is modeled by the inverse of the function P−1(t) = 20ln(40t − 1200), where t is measured
A worker is combining two chemicals used in a photography lab. Chemical R costs $0.17 per gram. Chemical T costs $0.32 per gram. The worker must make a batch of
use the information in each graph to write the equation for the graph.​
busco a moralescarmenma
Explain how the setting is used as a symbol in either The Scarlet Letter excerpts OR “The Fall of the House of Usher," including two pieces of textual evidence
Which of these is an effective way to encourage children to engage in conversation
What are 3 ways the Bill of Rights fulfills this purpose?