Crashing almost always accelerates the schedule while increasing project risk, whereas fast tracking almost always accelerates the schedule while increasing project cost.A. TrueB. False

Respuesta :

gerald4764
gerald4764 gerald4764
  • 24-01-2020

Answer: False

Explanation: Because fast-tracking doesn’t involve additional resources, it’s usually best to start with this technique while Crashing requires careful planning to prevent “panic mode” among the project crews and to avoid acceleration claims.

Answer Link

Otras preguntas

Read Fatima’s paragraph. Having moved up north just last year, I experienced my first snowstorm this past winter. At first, the snow twirled gently, lightly dus
Which statement would a member of the social gospel most likely agree with? A. "American Indians can only be assimilated through conversion." B. "A true Christi
Calculate the ratio of 3 nickels to 12 dimes.
Thesis on as merican identy
Solve:2/3 - 4x +7-2= -9.x +5/6 x = -3/2 x = -2/3 X=2/3 X=3/2
State three economic importance of mucor
What is the value of 3-(-2)
A company that manufactures video cameras produces a basic model and a deluxe model. Over the past year, 41% of the cameras sold have been of the basic model. O
When writing expressions for complex numbers, what does i represent?
A 48 meter antenna mast is stabilized by a 52 meter guy wire How far from the base of the mast is the guy wire secured to the ground A 20m B 50m C 60m D 100m