Which of the following terms is not used in project management? A. Dummy activity. B. Latest finish. C. Optimistic time. D. Lumpy demand.

Respuesta :

ahmedgodtrust
ahmedgodtrust ahmedgodtrust
  • 20-01-2020

Answer:

Lumpy demand is not used in project management.

The correct answer is  D

Explanation:

Dummy is a zero activity, which helps in network analysis.

Activity refers to a task in network analysis.                                                              

Latest finish time is the latest completion time of a project in network analysis.

Lumpy demand refers to low demand as a result of higher cost. It is not used in network analysis (project management)

Answer Link

Otras preguntas

When measuring length, 20 decimeters is greater than 20 centimeters. true or false?
What problems did early labor unions face?
Another name for a farmer could be a. george. b. geometrician. c. geometer. d. geographer.
Insulin is synthesized and released by the: brain. liver. pancreas. gallbladder.
how does the temperature affect the rate in which sugar dissolves ?
The patient begins to cough and choke as the nurse is inserting the ng tube. why would pulling the tube back and attempting to reinsert be the best action
what does ashanti mean
Kristin says that the product of 1.25 × 44 is 55. Surya says that Kristin's anwer is incorrect because the product must have two decimal places. How would you c
The passage of the fifteenth amendment in 1869 prompted the formation of two major sufferage organizations because
if a=3/2 and b=3/4 which of the following has the greatest value?